Oceanfront Seawall Armoring
Project type
Town of Manalapan Seawall Project
Location
Manalapan Florida
In Manalapan, the sea water over topped the sea walls, washed away the soil, exposed the concrete deadmen and the steel tieback anchors snapped. With its support system compromised, the steel sheet piles failed and fell toward
the ocean. Sea water flooded the oceanfront properties and caused significant damage to the ultra prime real estate.
Lands End & Skyline designed a T-wall system with the main wall at a height of 8 feet above the mud line, an increase from the previous height of 5 feet. To stabilize the sea wall, shorter steel sheets were driven into the limestone at 28’ to 30’ depth. The anchor walls were connected to the main wall using C9s.
The Project was Completed with he assistance of DEP, DNR and Army Corps of Engineers. Lands End Flew to Tallahassee to meet with DEP to Get fast track on permits due to Turtle season conflicts. We completed 2 miles of Steel sheet pile removal and replacement including pouring 2 miles of 4'X 4' concrete cap on top of the sheet piles. Completed on time and within budget!